Do you need planning permission?
In England, most roof-mounted solar panels on houses are permitted development, so you don’t need planning permission. There are exceptions:
- listed buildings
- some homes in conservation areas, especially on roofs facing a road
- flats and commercial buildings, which have different rules
- ground-mounted systems above certain sizes
We check your property before we quote and tell you if an application is needed.
Grid approval: G98 and G99
Every system connected to the grid must be registered with the local network operator. Across Dorset, Hampshire and Wiltshire that’s SSEN. Smaller systems are notified after installation under G98. Larger systems, and most systems with a battery, need approval under G99 before connection. We prepare and submit the paperwork for you.
With your written consent, we submit the G99 application as soon as you accept your proposal, so the approval clock starts straight away. You keep your 14-day right to cancel.
Why MCS certification matters
MCS certification shows a system has been designed and installed to the industry standard. You need an MCS certificate to receive Smart Export Guarantee payments for the electricity you export. We’re MCS certified (certificate 69555) for solar PV and battery storage.
Building regulations
Electrical work is certified under Part P through NAPIT, and we check the roof structure can take the weight of the panels.